Thursday, October 13, 2016

10-13-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Traffic Markings
Fraction of Day workable 10/10
AM Partly Cloudy PM Mostly Sunny
Hi 64 Lo 48

Reith Riley Had a Concrete crew working on the South east Corner of Washington and Main. They had a second crew working on the south half of the Library drive. A third crew worked on the North west corner of  Main and Wayne, that same crew worked on the north east corner of Wayne and Main.

Reith Riley had a prep crew finish the Pave drain on the East side of Main Street. They then worked on cleaning up the downtown area. a second crew worked on clean up and fixing temporary crosswalks on Saint Joe Street.

Pemberton Davis worked on setting light poles on the west side of Main from Colfax to Wayne. They also worked on getting lighting up and running on Michigan between ewing and Sample. 

Indiana earth worked on removals on Michigan from Wayne to LaSalle on the West side of Saint Joe. They had two crews working on this 

Air Marking worked on the Epoxy paint between Bronson and South Street. They had a second crew working on the detail work from Ewing to Sample on Michigan and Main. A third crew worked on the layout of the down town area. 

Woodruff worked on structures on Saint Joe Street between Wayne and LaSalle on the west side. 