Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Asphalt
Fraction of Day workable 10/10
AM Mostly Sunny PM Mostly Sunny
Hi 68 Lo 44

Reith Riley had a crew paving Main street from South Street to LaSalle. They also paved the approach on the east side of Main at Wayne.

They had a concrete crew working at the intersection of South Street and Main. They had another concrete crew working at the intersection of Main and Colfax east side North and South. A third crew worked on curb work on the east side of main on Washington Street.

Reith Riley had a prep crew placing pave drain on Main Street from Colfax to Wayne on the east side. A second crew worked on prepping for bicycle track from Jefferson to main on the east side. 

Indiana East worked on removals on the west side of Saint Joe between Washington and Colfax. A second crew worked on prepping on the east side of main between Western and Wayne . 

Pemberton Davis worked at the intersection of Colfax and main on the east side and Jefferson and main on the west side. Over night they removed the mono tube between LaSalle and Colfax on Main. They moved poles off of Saint Joe to Main Street and Colfax and Jefferson.

Slussers worked on placing mulch at the Marion and Bartlett roundabout. They also worked on prepping for sod on the South East and North East quad of Bartlett.

Air Marking worked on laying out traffic Markings on Michigan between Ewing and Sample.

Wisco worked on the irrigation on the west side of Main between Marion and Madison.

Woodruff worked on placing structures between Washington and Wayne on the west side of Saint Joe.  