Tuesday, October 25, 2016

10-25-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Curb
Fraction of Day workable 10/10
AM Sunny  PM Partly Sunny 
Hi 55 Lo 37

Reith Riley had a concrete crew pour concrete on the North East corner of Main and Jefferson. A second crew poured the bike pads north of LaSalle on Main and Michigan up to Marion. A third crew poured noses to the islands on Saint Joe Street between Western and Lasalle. 

Reith Riley had a prep crew working on paver bands on the east side of Main from LaSalle to Jefferson sweeping in the stone. A second crew worked on placing asphalt in the widening areas around the curb on saint Joe from Western to LaSalle. A third crew worked on prepping the concrete pours on Saint Joe.

Reith Riley had an Asphalt crew patching the electric conduit trenches at Bronson and south Street on Michigan. They then placed surface once it warmed up on Michigan from Sample to Western on the west two lanes.

CE Hughes milled Michigan from western to Sample on the east half of Michigan. Reith Riley had a crew cleaning up behind them.

Slussers placed sod at the Bartlett round about finishing up a lot of the loose end areas.

Woodruff worked on placing 2 structures at the South West corner LaSalle and Saint Joe. 

Pemberton Davis worked on conduit and footers on the east side of Main from Colfax to Western. they also worked Bronson and Michigan.

Wisco worked on the west side of Main Street between Madison and Marion.\

Reith Riley aslo cored the water leak area between Monroe and South street.