Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Curb
Fraction of Day workable 10/10
AM Sunny  PM Partly Sunny 
Hi 58 Lo 43

Reith Riley had a concrete crew working on the intersection of Jefferson and Main St. East side they also poured Bike Path from Jefferson to Washington on the East side. A Second Concrete crew worked on pouring the rest of the Double Tree driveway ( north Halves ). A third crew worked on pouring the island curb on Saint Joe. Street from Colfax South to Wayne. A fourth crew worked on pouring the radius-es on the Islands from LaSalle to Washington on Saint Joe.

Reith Riley had a prep crew placing cycle track pavers on the east side of Main street from LaSalle to Washington. A second crew worked on prepping the South west corner of Main and western. When that was completed they started placing asphalt on the corner patches at western and Wayne. 

Indiana Earth had 3 crews working on grading behind the curb from Western to LaSalle on Main Street east and west side of the road.

CE Hughes milled for the patching on Michigan from Sample to Bronson. They hit an old railroad track about 300 feet south of Bronson street. The track set in the 2nd lane from the right and was roughly down 4 inches. Once the patching was completed they surface milled the western 3 lanes from Sample to under the bridge at Bronson.

Reith Riley had an Asphalt crew placing the patching behind CE Hughes from Bronson to Sample on Michigan. They then went and placed asphalt at the curb cuts and radio-uses on Michigan from South Street to Sample.

Reith Riley had a prep crew following the Milling on Michigan from Sample to Bronson.

Slussers had a crew prepping for sod on Bartlett Street east of Michigan and West of Michigan. 

Pemberton Davis worked on placing conduit at the intersection on Bronson and Michigan. They also worked on placing the conduit from the vaults to the Tesco cabinets on Michigan at Bronson and South Street. 