Wednesday, October 19, 2016

10-19-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Curb
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 74 Lo 48

reith Riley had a concrete crew working on cycle track on Main Street from Jefferson to Wayne on the east side. A second crew worked on cycle track from Colfax to Jefferson on the east side of Main. A third crew worked on pouring curb on Saint Joe street from Jefferson to Colfax on the west side of the road.

Indiana earth worked on removals at the corner of Wayne and Main. They also worked on setting grade on the curb on the west side of saint Joe from LaSalle to Colfax. 

Reith Riley had  2 prep crews working on setting the cycle track pavers from Marion to Colfax on the west side of Main.

Pemberton Davis worked on the pulling wire on the west side of Main street from LaSalle to Jefferson. They set hand holes on the east side of Main from Wayne to Colfax. they removed the lights at the corner of Jefferson and Main took them to the city. they poured foundations on the east side of Main.

Air Marking had a crew working on details on Main Street from Marion to South Street,

Wisco was in and worked on placing sleeves to the center islands on Saint Joe between LaSalle and Wayne. 

Metronet needs lowered at the corner of Jefferson and Saint Joe South west.