10-5-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 79 Lo 62

Reith Riley had an asphalt crew working on Michigan from Ewing to Sample Paving the west half. they also had a prep crew cleaning and a crew placing joint adhesive.

Reith Riley had a prep crew placing aggregate for the pave drain between Colfax and Washington. A second prep crew worked on grading for bicycle track on the east side of main between Western and Wayne. A third crew worked on placing the Pave drain from Jefferson to Wayne on the west side and they  went back and fixed Main between Madison and LaSalle on the west side.

Reith Riley had 2 concrete crews hand pouring curb on the east side of Main between Washington and Jefferson and they started on to Jefferson to Wayne. A third crew pored the last approach on the west side of Main between Jefferson and Wayne. They then went and poured header curb from Washington to Jefferson on the east side of the road. A fourth crew poured the the middle driveway to the parking garage between Jefferson and Wayne on the east side.

Woodruff worked the east side of main from between Jefferson and Wayne to between Wayne and Western. they finished the intersection of Main and Wayne on the east side.

Pemberton Davis worked on placing the poles at the intersection of Wayne and Main. 

Wisco worked on the round about at Marion.