Tuesday, October 11, 2016

10-11-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Asphalt
Fraction of Day workable 10/10
AM Mostly Sunny PM Mostly Sunny
Hi 74 Lo 54

Reith Riley had an Asphalt crew paving Main Street from LaSalle to South street on the North Bound Lane. They then started paving intersections going from the North to the South. A second crew worked on patching the curb line on the east side of Main from Jefferson to Wayne street. they then went down and patched the corners of Main and Indiana.

Reith Riley had a concrete crew working on the South west corner of Main and Washington and a crew on the north west corner of Main and Jefferson. They worked on the South East corner of Main and Colfax. And the worked on the south west corner of Main and Wayne. 

 Pemberton Davis Activated Hawk Signal and took the poles down at Broadway and Michigan. and worked on the foundations on the west side of Main Street from LaSalle to Wayne.

Indiana Earth worked on Saint Joe saw cutting and removing the islands on Saint Joe Street from Jefferson to Colfax. They also did miscellaneous work on Main.

Air Marking was in and epoxy painted the North Shore Bridge and Main Street between Bronson and South Street. They also had a detail crew working on Main Street from Sample to Ewing. They had a crew doing layout work on Michigan from Ewing to Sample and a Long Line crew placing the yellow on Michigan from Sample to Ewing.

Wisco worked on the west side of Main Street between Marion and Madison.

Woodruff worked on placing structures on Saint Joe. Street between Jefferson an Colfax on the west side of the street,