Tuesday, October 18, 2016

10-17-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Traffic Markings
Fraction of Day workable 10/10
AM  Sunny windy PM Mostly sunny windy
Hi 84 Lo 62

Reith Riley had a concrete crew working on pouring cycle track on the east side of Main from Colfax to Sample. A second crew poured cycle track from Jefferson to Washington on the east side of Main. A third crew worked on pouring curb on Michigan at the intersection of Monroe and Western west side. A fourth crew poured island curb on the Saint Joe from Jefferson to Washington.

Reith Riley had prep crew working on Cycle track from LaSalle to Jefferson on the West side of Main. 

Indiana Earth worked on grading out for curb on Saint Joe Street from Jefferson to LaSalle on the west side of the road.  

Slussers was on site doing plantings at Bartlett and Mulch.

Pemberton Davis worked on setting lights on the west side of Main from Jefferson to Wayne. They also worked on placing conduit and digging foundations on the east side of Main from LaSalle to Colfax.