Friday, October 21, 2016

10-21-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Curb
Fraction of Day workable 10/10
AM Sunny  PM Cloudy 
Hi 68 Lo 48

Reith Riley had a concrete crew working on the west side of Main between LaSalle and Colfax finishing the cycle track. A second crew worked on the North East corner of Main and Jefferson. A third crew worked on the west side of Saint Joe at the intersections of Wayne and Western. 

Reith Riley had a curb crew onsite working on the west side of Saint Joe between Washington and LaSalle.

Reith Riley had a prep crew working on placing paver bands on the West side of Main street between Jefferson and Western they also worked on the east side of Main between Wayne and LaSalle.

Pemberton Davis worked on the intersection of Jefferson and Main placing conduit and changing out heads and poles.

Indiana Earth worked on grading out for curb on the west side of Saint Joe from Colfax to LaSalle.