Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Traffic Markings
Fraction of Day workable 10/10
AM  Cloudy PM partly Cloudy breezy
Hi 76 Lo 62

Reith Riley worked on Pouring cycle track from Jefferson to Washington on the east side of Main. A second crew worked on pouring cycle track and side walk on the east side of Main between LaSalle and Colfax. A third crew worked on puring curb at intersections of Michigan and Western, Michigan and Monroe.

Reith Riley had two prep crews working on setting cycle track pavers from Marion to LaSalle on the East and west side of Main street. 

Pemberton Davis worked on setting light on the west side of Main from Western to Wayne. They dug foundations from LaSalle to Colfax on the east side of Main and the worked at placing conduit a the south east corner of Main and Colfax.

Air Markin placed stop bars and crosswalks on Main Street side roads from South Street to Marion.

Indiana earth worked on grading out for curb on the west side of Saint Joe from Colfax to Washington.