Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 8/8
AM Mostly Sunny PM Mostly Sunny
Hi 63 Lo 44

Reith riley had a concrete crew pouring sidewalk at Bronson east of Main. A second concrete crew worked on pouring header curb between Wayne and western on the east side of Main. A third crew poured curb on the North East and south East corners of Main and Western.

Reith Riley had a prep crew placing pave drain between Colfax and Washington on the east side of Main. A second crew worked on prepping the asphalt surface om Main from LaSalle to Wayne.

Pemberton Davis worked on placing conduit on the east side of Main from Western to Jefferson.

CE Hueghs is working on milling Main Street from LaSalle to Wayne on the east side.

The color run took place today. it started at 9:00 am and was completed at around 10:40 am. The only issues with the run was due to all the cross streets being closed it caused added traffic on Main Street.   