10-20-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Curb
Fraction of Day workable 6/10
AM light rain PM light rain
Hi 72 Lo 48

Reith Riley had a crew working on the north west corner of Jefferson and Main placing curb. They had a second crew working on the south east corner of Main and Wayne. They went home early due to rain.

The curb machine was broke down and they where unable to pour any curb.

The prep crew worked on placing cycle track pavers from Wayne to Lasalle on the west side of main.

Slussers was in and worked on plantings on the north side of Bartlett west of Michigan.

Pemberton Davis worked at the intersection of Jefferson and Main they removed the street lights on the west side of main and placed conduit on the east side of main. They also finished hooking up the traffic lights on the west side of Main from Lasalle to Western