Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Traffic Markings
Fraction of Day workable 10/10
AM  Cloudy PM Mostly Cloudy
Hi 74 Lo 52

Pemberton Davis worked from Midnight to Noon to finish the traffic signals to get them working for two way traffic. They worked on the intersections of Jefferson, Washington, Colfax and LaSalle on main Street. They removed the one way signs from sample to LaSalle on Main.

Air Marking was in and placed the last of the stop bars and turn arrows on Main Street. They then left at 10:00 to go work on Jefferson Street project. 

State Barricade opened up Colfax to Sample at 10:30 then opened Colfax to LaSalle at 11:30 once Pemberton Davis was done.

Tony was the only one onsite for Reith Riley. 

Wisco had one man working at Marion and Michigan.

No other work was preformed today.  