Wednesday, October 26, 2016

10-26-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Curb
Fraction of Day workable 00/10
AM Rain Cloudy  PM Cloudy Rain 
Hi 54 Lo 45

Reith Riley had a concrete crew show up and saw cut joints on Main Street. They then left due to the rain.

Reith Riley had an asphalt crew place base and binder along the curb on Saint Joe from Washington to Colfax. They also worked a short day due to the rain.

CE Hughes worked on Milling the west side of Saint Joe Street from Western to LaSalle.

Reith Riley had a prep crew cleaning up behind the milling operation on Saint Joe.  

Pemberton Davis did not work today.

Woodruff did not work today.

Slussers did not work today.

Air Marking did not work today.

No comments: