Friday, October 14, 2016

10-14-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Traffic Markings
Fraction of Day workable 10/10
AM Partly Cloudy PM Mostly Sunny
Hi 72 Lo 42

State Barricade worked on opening up Main Street and Michigan Street from Ewing to LaSalle. Michigan was opened at around noon and Main was opened around 1:30. message Boards where placed at Main and Ewing and on Main and Ewing and Main and Sample.

Air Marking  had a crew working on the details on Michigan from Ewing to Sample, They then went to Main Street around 2:00 and Sample and placed the turn arrows. they then went to Marion on Main and worked South word. A second crew did the long line on Main Street between South and LaSalle Streets.

Reith Riley poured Concrete at LaSalle and Main on the South East Corner. They had a second crew pouring cycle track from Colfax South the the parking garage on the east side of Main. A Third Crew worked on Pouring Cycle track from Washington North on the east side to the Parking Garage.

Indiana Earth worked on removals on Saint Joe Street on the west side  between Colfax and LaSalle. A second crew worked on grading for curb on the west side of Saint Joe between Jefferson and Washington.

Woodruff finished setting structures on the west side of Saint Joe between Wayne and LaSalle. They will be back when they can finish the east side of Saint Joe.

Pemberton Davis worked on placing and removing signs on Michigan and Main Street between Sample and Ewing. They also worked on pulling wire for the light poles on the west side of Main street. They worked on trying to cut the loops at Angela. The locations that ed Gleckler had for the detector housing was incorrect and required Pemberton Davis to abandon the operation until Monday when traffic will be less.  


Meeting Agenda
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
10-14-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1.       Traffic Closure Updates
A.           Bronson and South Street: South Street opened yesterday and Bronson Street will remain closed to the east of Main until November 15th.

B.           Colfax/Jefferson/Washington/Wayne: side streets will see minor delays only when work takes place on the corners. Washington will close in 2 weeks when woodruff is back in to do the structure at Washington and Main.

C.       Saint Joe: Saint Joe will remain 1 lane until November 15th and the side                           streets will see delays of 20min while concrete curb is being poured next week.
                                               
C.           Michigan and Main will open today from Sample to Ewing and Main Street will open tomorrow from Sample to Marion for two-way traffic.
Utility Relocation Issues:
AEP:  

Robert Henry:  Robert Henry and AEP will be redoing the schedule for Michigan Street from Washington to Western. They will work from the North to the South. Trying to work on Washington while it is closed with JMS. The intersection of Monroe and Main will need to be worked on that time is yet to be determined.

NIPSCO/InfraSource:   
            
Comcast: 

                AT&T:     The Main hole in the parking Stall between Colfax and Washington was determined to be an old Steam vault. The casting will be removed and the vault filled in with flowfill.

Water Dept:     The water department needs to adjust some valves at the intersection Jefferson Wayne and LaSalle on Saint Joe. A meeting on sight Monday will be held to review the traffic control. The water dept. would also like a no left turn be placed at the office at Colfax and Main St. Drive up window.

Transpo:   Wants to make sure the timings on the signals at South and Bronson on Michigan is being addressed.   
               
Metronet: No issues   
                 

Utilities Q/A

INDOT: Questions:    Did not attend

Stakeholder Questions: Larry would like the block moved from in front of the door to the building that sets on Madison east of Michigan.

Chase tower concerned over getting between cub and building to remove canopy and brick face.

311 wanted to confirm street name signs being placed back at Michigan and Broadway

10:00 am 10:10 Break Utility and Stakeholders can leave


Action Items
               
1           Upcoming work for the week: continue to work on the crossings and cycle track on Main Street. Start prepping for blocks and pavers between the curb and cycle track. Continue to work on the traffic and street lighting on Main Street. Pour curb on Saint Joe. Start milling and paving on the 24th on Michigan from LaSalle working north. Finish up the cross walks and side walk at Chippewa.

2           Cross Walks/completed on Main: Reith riley will try to complete the cross walk on Main Street and they Maintain cross walks on Saint Joe.

3           Signs/ status/speed limit Change order: Pemberton davis will remove signage and place new signs on the opened portions as quickly as possible.
       
4           Light pole footer claim /change order: The claim will be reviewed and responded to in writing at the first of next week. No penalties will be enforced due to the lighting not being completed as long as Pemberton Davis continues to work on it and it is completed as soon as possible.

5           Oct. 15 expectations and penalties: Stop bars, turn arrows, lane lines, Cross walks and traffic signals on Main St. with the exception of Bronson are all up and functioning. No penalties will be enforced on Main Street obligations have been met.

6           Strain Poles and cabinets due in: Division A is expecting the Cabinets in around November 1. Division B Pemberton Davis is expecting the Strain poles and cabinets in the second week of November. A meeting will take place one day next week to look at the constructability of the LaSalle and Michigan Corner and keep traffic signals working. I will forward on a signed copy of the change order to Reith Riley and Martell.

7           Next meeting every other week: The next Progress Meeting will be held in two weeks on a trial bases.


                                               
Reith Riley Construction Concerns/Questions:

Reith riley would like to get portions of the contract substantially complete before winter and give them back to the City.

City Concerns/Questions:

Need to look at the ped head at Main and Ewing pole appears in the way.                             
Make sure stripping on side streets is placed correctly (Jefferson is incorrect)

 Next weekly progress meeting 10-28-16





No comments:

Post a Comment