Monday, October 3, 2016

10-3-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM Cloudy PM Cloudy
Hi 71 Lo 58

Reith Riley had a crew milling Michigan Street From Ewing to Sample. 

Reith Riley had a asphalt crew patching back the intersection of LaSalle And Main, Colfax and Main, Jefferson and Main and Wayne and Main.

Reith Riley had a prep crew cleaning up the Milling operation. They also had a prep crew working on the Pave drain setting mats on Main Street from Washington to Colfax on the west side.

Reith Riley had a concrete crew pouring sidewalk on the east side of Main from Colfax to LaSalle. they had a second  crew pour the rest of the Transpo driveway, that same crew then worked on Bronson sidewalk. A third concrete crew worked on corners and ramps at the intersection of Indiana and Michigan, they also poured some sidewalk in front of the library. A fourth crew worked on header curb form Colfax to Washington on the east side.

Woodruff worked on the east side of Main at the intersection of Jefferson and headed south.

Indiana earth was working on rough grading between Washington and Jefferson on the east side. They worked on removals on Michigan street on the east side of South street. 

Pemberton Davis worked on conduit on the east side of Main street between Jefferson and Washington.They also set light pole foundations on the west side of Main street.

Wisco was in and working on various locations.