Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 8/10
AM Cloudy light rain PM Cloudy Light Rain
Hi 71 Lo 58

Reith Riley had a concrete crew working on pouring the drive to Transpo on the east side of Main street. They had a second crew working on pouring sidewalk on Bronson east of Main Street. A third crew was pouring side walk on the east side of Main Street between Wayne and Western. A forth crew poured the second half of the Morris civic drive on the east side of main and then worked on side walk between LaSalle and Colfax on the East side. 

A curb crew worked on the North east corner of Colfax and Main.

Reith Riley had a prep crew working on placing pave drain on the west side of Main Street between Colfax and Washington. A second prep crew worked on prepping for curb between Washington and Jefferson.  

Pemberton Davis was working on light pole foundations from Colfax to Jefferson.