Saturday, October 22, 2016

10-22-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Curb
Fraction of Day workable 10/10
AM Partly Cloudy  PM Partly Sunny 
Hi 61 Lo 43

Reith Riley had a concrete crew working on pouring the parking stalls on Saint Joe between Wahsington and Jefferson. They had a second crew working on the north driveway at the double tree. A third crew worked at pouring the Curb at South Street and at Wayne Street on the west side of Saint Joe Street. Reith Riley had the curb crew using the Machine pouring the islands from Washington Street to to LaSalle on Saint Joe. 

No other crews worked on the project for Reith Riley today.

Pemberton Davis only had Phil onsite.

Indiana earth was not on site. 

Air Marking was on site laying out the side streets from Lafayette to Saint Joe.

No comments:

Post a Comment