10-27-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Curb
Fraction of Day workable 10/10
AM Cloudy  PM Cloudy 
Hi 54 Lo 45

Reith Riley had a crew on Saint Joe Street pouring the curb on the South West corner of Jefferson, they also poured the nose to the island between Jefferson and Wayne on Saint Joe. A second crew worked on Island that goes into the Morris/ Michigan and Saint Joe Street. A Third crew worked  on the South East Corner of Main and Jefferson. 

Reith Riley had a prep crew working on the on the corners of Saint Joe prepping for ramps and side walk.

Reith Riley had an Asphalt crew in and they paved surface on Michigan from Sample to Western on the east half of the road.

Pemberton Davis worked on lighting foundations on the east side of Main from Washington to Wayne. They also worked on lowering the hand hole on the south west corner of Saint Joe and Jefferson

Wisco worked on the west side of Main street between Marion and Madison.

Indiana Earth worked on the west side of Main street between Washington and Western setting grade for the pavers that go in between the side walk and curb. They had a second crew working on Saint Joe from Washington to Colfax grading out for the sidewalk.