Wednesday, August 31, 2016

8-31-16

Controlling Operation Bartlett: Lighting
Controlling Operation Marion: Center Aprons and Curb
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Sunny  PM Cloudy
Hi 78 Lo 65

Rieth-Riley had a concrete crew that poured two approaches on the west side of Main St. between Madison and LaSalle on the west side and the South McDonald's approach on the east side of Michigan between Madison and Marion. They also poured the curb ramps at the northwest corner of the intersection of Main and LaSalle.

Indiana Earth continued removals on the east side of Michigan between Madison and LaSalle.They also worked on grading out the subase of the east side of Michigan between Marion and LaSalle.

Pemberton Davis was installing the base lights in the center of the Marion roundabout. They also worked on street lights on Main Street west side. 

WISSCO was working on irrigation on the west side of Michigan north of the Marion roundabout.

Air Markings painted temporary striping on Michigan St. from Angela to Marion and on Main St. from Marion to LaSalle and on Main from Bronson to Sample.

Reith Riley installed Pave Drain in the parking bay on the east side of Main St. North of Madison.

Reith Riley poured the 4' apron around the monument footing inside the Marion roundabout walls.

Zoilkowski placed the cap on the Marion Street Round about.