Tuesday, August 23, 2016

8-23-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Mostly Sunny  PM Mostly Sunny
Hi 80 Lo 59

Rieth-Riley had a concrete crew pouring cycle track on the south side of Marion and the east side of Main between Madison and Marion. Subbase was also placed in the sections of Main St. between LaSalle and Marion where PaveDrain is to be installed. A second crew worked on grading out the splitter islands at Marion,

Another Rieth-Riley concrete crew poured sidewalk at the northwest corner of the Marion roundabout and poured the colored concrete splitter islands of the Marion roundabout. 

Rieth-Riley also had a curb crew pouring curb on the west side of Main south of Western.


Ziolkowski continued placing the brick veneer on the Marion roundabout walls.

JPR was on site staking for curb on the west side of Main between Colfax and Washington.

Indiana Earth had a crew removing the east side of Michigan St. between LaSalle and Madison. They had a second crew placing top soil around the inner circle of the Bartlett Round About. They also worked in the down town area grading. 


Wisco was on site working at the Bartlett round about South east quad.