Wednesday, August 24, 2016

8-24-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 7/10
AM Cloudy  PM Rain from 12-2, Cloudy
Hi 81 Lo 67

Rieth-Riley had a concrete crew that poured cycle track on the east side of Main north of Madison. They also poured the north splitter island of the Marion roundabout and began forming for cycle track on the west side of Main south of Madison.

A second Rieth-Riley crew formed the upper apron of the Bartlett roundabout.They poured half of the upper ring concrete and they also poured the splitter island north of Marion on Michigan. 

Rieth-Riley also had a asphalt crew that paved the section of Marion directly east of the roundabout, as well as approaches on Michigan between Angela and Riverside. 

Ziolkowski continued placing the brick veneer for the roundabout walls in the Marion roundabout. 

WISSCO was on site at the Bartlett roundabout working on irrigation.

Pemberton Davis was working on lighting on the west side of Michigan between Marion and Madison.

Indiana Earth was grading for landscaping near both the Bartlett and Marion roundabouts. 

No comments:

Post a Comment