Friday, August 26, 2016

8-26-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Mostly Sunny  PM Sunny
Hi 82 Lo 64

Rieth-Riley had a concrete crew that poured the colored concrete for the splitter islands on the west and south sides of the Marion roundabout. Then they worked on setting the cages and doing prep work for the lower truck apron of the Bartlett roundabout.

A second Rieth-Riley crew poured sidewalk on the east side of Main between Madison and LaSalle.

JPR was on site staking the east side of Michigan from Madison to LaSalle for curb.

Woodruff worked on setting storm structures on the east side of Michigan south of the Marion roundabout.

Ziolkowski continued placing the brick veneer at the concrete walls in the center of the Marion roundabout and the wall caps are ready for installation.

Indiana Earth was removing pavement on the south side of Marion east of Michigan.

WISSCO was working on irrigation at the southeast quadrant of the Bartlett roundabout. 