8-15

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 6/10
AM Cloudy Rain  PM  Rain starting 1:30pm
Hi 76 Lo 67

Reith Riley had a concrete crew pouring side walk at Bartlett street on the south east quad and the south west quad trying to get the hospital back in service. A second concrete crew poured sidewalk in front of the water department and they poured crosswalks at the Marion roundabout. They then set forms for side walk on the south west quad of Marion and Michigan.

Reith Riley had a prep crew working on grading in front of the Mar main apartments. They then moved down to Bartelett and graded out on the east side by the doctor office,

Reith riley had a milling crew working on milling from Bronson to Sample on Main Street. They then went and placed mix around manholes north of Bartlett on Michigan.

Indiana Earth worked on removing dirt from Bronson to South Street on Main so that the subgrade treatment  can take place. They also graded out the south west quad of Michigan and Marion so the sidewalk can be placed.

Pemberton Davis removed the Mast arm on the North west corner at Jefferson and Michigan to assist the motel work going on at that corner.

Wisco was on site working Between Main and Michigan south of Bartlett by the Hospital.

Found a Metro Net lateral on the north east corner of LaSalle and Main, Pemberton Davis will set a handhole then Metro Net will move the cable. 