Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Mostly Sunny PM Sunny
Hi 89 Lo 64

Rieth-Riley had a concrete crew which poured the southbound lanes of Michigan St. south of the Marion roundabout and the eastbound lanes of Marion St. east of the Marion roundabout. In the afternoon they began forming the northbound lanes of Michigan south of the roundabout. This section will be poured tomorrow, which is the final section of concrete pavement in the Marion section. 

Indiana Earth continued removals on the south side of Colfax where the new Saigon drive will be located. Removals also continued on the east side of Main between South and Bronson. 

Ziolkowski continued prepping the formwork for the roundabout walls in the center of the Marion roundabout. A second Ziolkowski crew continued placing the brick veneer on the Bartlett roundabout walls. 

Pemberton Davis set mast arms at the intersection of Main and Sample.