Saturday, August 27, 2016

8-27-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 0/10
AM Thunderstorms  PM Cloudy, Rain
Hi 82 Lo 69

Rieth-RIley had two concrete crews, a curb crew, and two asphalt crews in the morning. 

The asphalt crews began paving surface pavement at the intersection of Main and Marion and on the east side of Main just south of Marion. 

The approaches to the Bartlett garage were milled and base was put back in. 

One of the concrete crews poured a section of sidewalk on the west side of Main between Madison and LaSalle.

Rain forced crews to stop work around 8 am and crews were sent home at 9:30.