Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 9/10
AM Cloudy PM partly Cloudy Rain 3:30
Hi 92 Lo 71
Rieth-Riley had a concrete crew pouring the curb ramp at the southeast corner of the Michigan and Madison intersection. They also poured the drives east of Main on Madison. A second concrete crew poured the color concrete on the North South Spliter islands of Bartlett.
Reith Riley Milled North of Bartlett to Angela Blvd on Michigan.
Reith Riley paved from Bartlett to Marion on Michigan
Pemberton Davis worked on setting the mast arm foundation at the southwest corner of Main and Colfax They also worked on the recessed lights at Bartlett.
Ziolkowski continued setting the capping blocks and Planters on top of the Bartlett roundabout.
Indiana earth worked on subgrade treatment at the Underpass between Bronson and South Street. They graded out the west side of Main between Washington and Wayne. They also worked
Wisco was on site and worked at the Bartlett round about.
Weekly Progress meeting was held see below for Minutes.
Meeting With:
|
|
|
|
Meeting Date:
|
|
|
|
Regarding:
|
|
|
Construction and
Utilities
|
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
Michigan road will have lane restrictions north of Bartlett
to Angela Boulevard during the resurfacing operations, which should be
completed by Wednesday. Main Street will have lane restrictions from Bronson to
Sample Monday thru Thursday of next week for resurfacing. Metro Net has
completed their work at Jefferson and Main Reith Riley will have the
intersection opened by Monday.
Utility Relocation Issues:
Robert Henry:
Robert Henry will be working on Main Street between Monroe and South
Street on the east side, should be done by next week. They also have work on
east Washington that should wrap up next week. Robert Henry will adjust the
structure at the North East corner of Michigan and Marion as soon as Reith
Riley gets grade stakes set.
NIPSCO/InfraSource:
Nipsco is working on
lowering the gas line south of Bronson, which should be completed today.
Comcast:
Comcast emailed that they will be contacting Tony for Reith riley about
the work on Marion east of Michigan.
Water Dept.:
The water Department is working on adjusting castings on Main Street,
they are complete from Marion to Wayne. They are going to go down and work from
Sample to Bronson next to accommodate Reith Riley’s paving. They are also going
to go to Chippewa on Monday and relocate a fire hydrant at the Northeast corner
of Main and Chippewa. The water
department requested that the sidewalk in front of the office on Main and
Colfax have the sidewalk poured back as soon as possible.
Transpo: Had no issues
Metronet:
Metro Net and the City have an agreement
to remove the WIFI for the downtown area. Before removals of the traffic
signals, start that the Wi-Fi is connected to Metro Net will need a couple
days’ notice. Metro Net also so requested that a new conduit be run from
LaSalle to Marion due to the quality of the current conduit.
INDOT: Questions
INDOT requested an update of the
traffic restrictions. The three round-about’s will be open on Sept 7th.
Main from LaSalle to Western will be completed by Oct 15th. Saint
Joe from Western to LaSalle will be completed Nov 15th.
Stakeholder
Questions:
The new
landscape plans were presented to Memorial Hospital. Larry requested that the
plans be revised to consider the Hospitals new signage, as to not have the
trees block the signs. He had concerns about the public access points to the
Hospital when would they be complete. He also had concerns about the traffic
control associated with the milling operation between Bartlett and North Shore.
Action Items
Schedule
The upcoming week Reith riley will
pave from Marion to Angela. They will move down and pave from Bronson to Sample
on Wednesday. They will have a concrete crew finishing the sidewalk at the
Bartlett street intersection. Then move to the truck apron concrete. The curb crews will be in and work in the
downtown are on Tuesday. Another concrete crew will be working on the cycle track
and sidewalk from Marion to LaSalle. Indiana earth will be working on preparing
the grade between the sidewalk and the curb in the downtown area on Main Street
from Colfax to Wayne. Indian earth will also finish setting grade on Main
Street from South Street to Bronson once that is complete Reith Riley will
place the subgrade treatment.
1 Work on Saint Joe/ Monroe/
Western
Pemberton Davis still has traffic
signal work to do. Roger requests temporary sidewalks be placed since the
sidewalks have been removed for 2 months.
2. Entrance to 5th/ 3rd Bank
Reith Riley will work on making
sure the subs do not block both entrance to the bank.
3. Strain Pole Change order
Should be signed and on Toys deck
by Monday
4. Crosswalks on side streets
Crosswalks on the side streets
needs to be kept up for pedestrians. Reith riley will have a crew on
Saturday work on some of them.
5. Work on the East side of Main/ Parking
Garages
Reith Riley and the City will meet
on site Monday to go over access and egress from the parking garage at Colfax.
Reith Riley Construction
Concerns/Questions:
1.
Reith Riley is concerned the overhead structure
South of LaSalle will fall into the cycle path. Once it is laid out, the City
will have to determine what to do.
2.
The Pave drain mats will leave a void at the
header or the curb. The solution is to add another half bock to one side. This
will result in the header being reduced by 6 inches.
City
Concerns/Questions:
The
City stressed getting the drives and crosswalks in for pedestrian traffic can
flow in the downtown. The lack in activity in the downtown area over the last
few weeks has caused the public to become frustrated.
Next weekly progress meeting 8-19-16
No comments:
Post a Comment