Thursday, August 4, 2016

8-4-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Mostly Sunny PM Sunny
Hi 91 Lo 74

Rieth-Riley had a concrete crew that poured the northbound lanes of Michigan St. which are the south approach to the Marion roundabout. All concrete pavement in the Marion section is now complete. The crew spent the afternoon forming the new driveway for Saigon Market. The driveway will be poured tomorrow morning.

A Rieth-Riley curb crew poured curb on the west side of Michigan St. between Madison and Marion. In the afternoon they moved to the west side of Main between LaSalle and Colfax.

Rieth-Riley has an ashpalt crew that patched the intersection of Michigan and Madison.

Indiana Earth had a removal crew doing removals on the east side of Main between South and Bronson.

Ziolkowski continued forming the concrete walls at the Marian roundabout and placing the brick veneer at the Bartlett roundabout.