Tuesday, August 2, 2016

8-2-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Mostly Sunny PM Mostly Sunny
Hi 87 Lo 62

Rieth-Riley had a concrete crew which poured the remaining section of the Marian roundabout pavement. They then formed the south approach to the Marian roundabout.

A second Rieth-Riley crew poured curb on the west side of Main between Wayne and Jefferson. Staking has been performed from Jefferson to Washington.

Indiana Earth began removals on the souht side of Colfax where the new Saigon drive will be located. They also continued saw cutting on the east side of main. The east side of Main has been saw cut as far south as Western.

Ziolkowski continued prepping formwork for the roundabout walls within the Marian roundabout. At the Bartlett roundabout, Ziolkowski began placing the brick veneer on the roundabout concrete walls. 