Tuesday, August 9, 2016

8-9-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 88 Lo 60

Rieth-Riley had a concrete crew that poured sidewalk on the east side of Main between Madison and LaSalle. They also poured the Burger King approach on the east side of Main and did curb ramps at the northeast corner of the Madison and Main intersection. They also poured the concrete header for the parking lane on the east side of Main between Madison and LaSalle.

The Rieth-Riley prep crew was grading for cycle track on the east side of Main north of Madison, which included digging the trench for subbase materials under the paver band.

Woodruff was on site laying storm pipe and structures on the west side of Main between Madison and LaSalle. 

Ziolkowski removed the bracing from the roundabout wall formwork in the center of the Marion roundabout aznd completed most of the formwork striping.They also had a crew placing the cap at the Bartlett Round-about.

JPR was staking structures on Main Street between Bronson and South Street.

Indiana Earth was working on removals south of Bronson on Main Street. They also had a crew working on removing the Saigon drive that emptied onto Main Street.

The water department continued adjusting castings on the west side of Main St. downtown.

WISSCO was running pipe on the west side of Michigan between LaSalle and Colfax.

Pemberton Davis was installing the can lights alongside the crosswalks in the Bartlett roundabout. 