Saturday, August 20, 2016

8-20-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 8/10
AM mostly sunny  PM cloudy rain late
Hi 81 Lo 68


Reith Riley had a concrete crew pouring headers on Main Street between Madison and LaSalle on the west side. They then went to Michigan and poured headers on the west side between Madison and LaSalle. A second concrete crew was on site pouring side walk on the west side of Michigan between Navarre and Bartlett, They then worked on forming steps and side walk on the South East quad of Bartlett.

Robert Henry was on site adjusting Man hole lids on Michigan from LaSalle to Marion.