Wednesday, August 17, 2016

8-17-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM mostly sunny  PM mostly sunny

Reith Riley had a crew pouring side walk on the west side of Michigan from Madison North to Marion and East towards Main. A second crew worked on the South east corner of Bartlett and Michigan. They then went up and worked at the North west corner of Wayne and Main. 

Reith Riley's prep crew graded for side walk at bartlett and Michigan South East corner. They also clead up main street around Finigans, Fddlers and the oyster bar.

Indiana earth worked on removing dirt south of the tracks between Bronson and south street on Main. A second crew worked on removing curb between Park and Riverside. They then worked on grading out the inner circles for the colored concrete.

Pemberton Davis worked on the west side of Michigan between LaSalle and Marion doing street lighting.

Wisco worked on the Bartlett street irrigation.

Zoilkowski worked on placing brick on the Marion Round About.

United signs placed the welcome to South Bend sign.

Met with Kevin of Saigon about lack of curb.

No comments:

Post a Comment