Tuesday, August 30, 2016

8-30-16

Controlling Operation Bartlett: Lighting
Controlling Operation Marion: Center Aprons and Curb
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 7/10
AM Cloudy, Rain from 11:30 - 1 pm  PM Cloudy
Hi 83 Lo 69

Rieth-Riley had a curb crew that poured curb on the east side of Michigan from the McDonald's approach to the drive in front of the field office.

Rieth-Riley had a concrete crew that poured sidewalk and curb ramps on the west side of Main from Madison to LaSalle. A second crew began installing Pave Drain on the west side of Michigan St. between Marion and Madison.

Pemberton Davis was working on lighting at the Bartlett roundabout and also running conduit on the south side of Marion east of Michigan.

Ziolkowski continued installing the wall caps on the Marion roundabout center walls. 

WISSCO was on site at the Bartlett roundabout working on irrigation.

Reith Riley prep crew worked on drives on the east side of Michigan from Marion to LaSalle. A second crew worked on placing pavers in the parking stalls on Michigan west side.

Airmarking was on site laying out for striping

No comments:

Post a Comment