Monday, August 22, 2016

8-22-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Mostly Sunny  PM Mostly Sunny
Hi 76 Lo 56

Rieth-Riley had a concrete crew which poured the two levels of curb in the center of the Bartlett roundabout. They also poured sidewalk near Blair Warner and the outer walls of the concrete stairs on the south side of Bartlett west of Michigan.

Reith Riley had a prep crew working on the splitter island subbase for the Marion Round About. a second crew worked on preping side walk on the Northeast corner of Marion and Michigan,

A second Rieth-Riley concrete crew worked on sidewalk on the north side of Marian west of the MarMain alley. 

Rieth-Riley had an asphalt crew which paved Main St. between Bronson and Sample. They also patched the west side of the intersection of Jefferson and Main.

Rieth-Riley's milling crew which milled Michigan and Main St. between Madison and LaSalle.

Pemberton Davis was installing bi-directional flashers and signal and light pole foundations on the west side of Main St. between LaSalle and Marion.

Robert Henry was working on an electric duct on the east side of Main between South and Monroe.

Ziolkowski continued laying bricks for the roundabout walls in the Marion roundabout. 

Indiana Earth was on site doing removals on the east side of Michigan between LaSalle and Marion.They also worked on grading out in the downtown area for headers and parking.

Wisco was on site working on the Bartlett round about area. 