Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 91 Lo 66

Rieth-Riley had a concrete crew pouring sidewalk on the east side of Main between LaSalle and Madison. They also poured the curb ramp at the northwest corner of the Main and Madison intersection and an approach on the south side of Madison. The also stained the stamped concrete bands that cross the approahces on the west side of Main between Madison and Marion.

Rieth-Riley's prep crew continued grading the cycle track and paver band detail on the east side of St. Joseph St. south of Madison. 

Woodruff finished the pipework remaining on the west side of Main St. just south of Colfax. Then they installed trench drain for the approaches on the west side of Main St. between Madison and LaSalle.

Pemberton Davis continued working on can lights at the Bartlett roundabout crosswalks. They also worked at the intersection of Main and Colfax. There is a conflict regarding the placement of the mast arm foundation at the southwest corner of that intersection due to an existing electric duct bank. The new location is still being determined.

Indiana Earth finished removals at the intersection of Main and Bronson and also backfilled areas on the south side of Marion between Michigan and Main.

Ziolkowski continued setting the capping blocks at the top of the center walls of the Bartlett roundabout.

The water department continued adjusting castings on Main St. in the downtown area. 