Monday, August 8, 2016

8-8-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 85 Lo 62

Rieth-Riley had a concrete crew that poured sidewalk on the North side of Marion between Michigan and Main, and also on the east side of Main between Madison and LaSalle.

Rieth-Riley also had a curb crew that was pouring curb on the west side of Michigan between Madison and Marion until the curb machine malfunctioned and stopped operations.

Rieth-Riley's prep crew wedged the gaps in the Saigon drive with asphalt.

Ziolkowski poured the concrete walls in the center of the Marion roundabout. They also continued laying bricks on the center walls of the Bartlett roundabout. All exterior brick work is complete and tomorrow capping will begin. 

Pemberton Davis worked on lighting on the west side of Michigan between Marion and Bartlett.

Woodruff had a crew setting a fire hydrant on the west side of Main between Wayne and Western (this location needs to be verified).

Indiana Earth was doing removals on the east side of Main between Madison and LaSalle.

Wisco was on site working at various locations.

Metro Net got the conduit fixed at Jefferson and Main.  