Friday, August 26, 2016

8-25-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 9/10
AM Early Light Rain, Cloudy  PM Cloudy
Hi 80 Lo 66

Rieth-Riley had a concrete crew that poured the upper apron of the Bartlett roundabout with colored concrete.
They then went to Marion and worked on the splitter island concrete to the East and to the North. 

A second Rieth-Riley concrete crew poured cycle track on the east side of Main between Madison and Marion and also on the west side of Main at the northwest corner of the Main and Marion intersection.

The Rieth-Riley curb crew poured the mountable curb around the center of the Bartlett roundabout.

Reith Riley fog sealed the asphalt from Marion to Angela.

Pemberton Davis worked on the lighting in the center of the Bartlett roundabout. They also worked on light pole foundations on the west side of Michigan between Madsion and Marion. 

Indiana Earth continued removals on the east side of Michigan between Madison and Marion. Traffic was shifted to the far west lane of Michigan and traffic now flows through the southeast quadrant of the Marion roundabout rather than through the temporary road.

Reith Riley had a prep crew cleaning from Bartlett to LaSalle. A second prep crew worked on excavating for the outer edge of the paver bands from Marion to LaSalle on Main Street. 

Wisco was on site at the Bartlett Roundabout working on irrigation. 

Slussers was on site and mowed the weeds at Bartlett.