Thursday, August 11, 2016

8-11-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Cloudy PM Mostly Sunny
Hi 92 Lo 71

Rieth-Riley had a concrete crew pouring the curb ramp at the southeast corner of the Main and Madison intersection. They also poured the drives east of Main on Madison. A second concrete crew poured the color concrete on the East West Spliter islands of Bartlett.

Pemberton Davis worked on setting the mast arm foundation at the southwest corner of Main and Colfax.

Ziolkowski continued setting the capping blocks at the top of the Bartlett roundabout.

Woodruff was setting structures on the east side of Main St. between Bronson and South. 

Indiana earth worked on subgrade treatment at the Underpass between Bronson and South Street. They graded out the intersection of Main and Jefferson West side and they graded out the west side of Main between Madison and LaSalle. 

Wisco was on site and worked at the Bartlett round about.

Down Town Ras meeting was held today.