Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 9/10
AM Cloudy Rain  PM  Cloudy  
Hi 84 Lo 7

Morning rain caused the asphalt paving to be called off.

Rieth-Riley had a concrete crew pouring side walk on Michigan north of Madison on the west side. . A second concrete crew worked on forming side walk on the west side of Michigan between Marion and Navarre.

Reith Riley Milled North of Bartlett to Angela Blvd on Michigan doing the approaches. They then moved down and milled the intersection of Sample and Main Street.

Reith Riley had a prep crew working down town for the water department entrance and various locations down town. a second prep crew worked from Madison to to Marion on main prepping cycle track.

Wisco was on site working at Bartlett.