Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Partly Cloudy PM Sunny
Hi 82 Lo 64

Rieth-Riley had a curb crew that poured curb on the west side of Main St. between Western and Wayne. 

Another Rieth-Riley concrete crew poured curb ramps and sidewalk at the intersection of Main and Marian.

Woodruff was on site laying trench drain on Main St. between Madison and LaSalle. 

Traffic was flipped to the new southbound travel lane on Main St. south of South St. the east side of Main St is now closed between South and Bronson. 

Ziolkowski continued setting forms for the concrete walls in the center of the Marian roundabout. 