Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 5/10
AM Cloudy rain 11 am  PM cloudy
Hi 82 Lo 68

Reith Riley had a asphalt crew paving from North Shore to Angela.They stopped at 11 due to rain and restarted around 1 pm.

Reith Riley prep crew worked on prepping for headers on Main and Michigan from Lasalle to Marion.

The curb crew set string and waited out the rain and poured the curb from Park street to Riverside on Michigan. Another Concrete crew worked on pouring side walk at Bartlett South east quad and South West quad. A third concrete crew poured headers on Main from Marion to Madison. Then went to Bronson and poured pavement on the South end of Michigan to allow for asphalt paving to have a starting point.

Wisco worked on the Bartlett round about west half.

Indiana earth continued to grade the center colored concrete area at Bartlett, They also had a crew placing dirt in the Marion Round about. Another crew worked on the Main Street underpass. They saw cut for pavement removal on Michigan from Lasalle to Madison.

Hard Core was on site sawing the joints for sealing at Marion Round about.

Zolkowski worked on Laying brick at the Marion Round about.

Pemberton Davis worked on setting lights on Main Street from Madison to Michigan. They also worked on lighting at the Bartlett Round about.