Monday, August 29, 2016

8-29-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: Roundabout Wall
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Sunny  PM Sunny
Hi 85 Lo 69

Rieth-Riley had an asphalt crew that paved surface on Main St. from just south of Marion to LaSalle. They also paved the Madison St approaches to Main St. In the afternoon they wedged remaining sections of the Bartlett garage approaches and paved surface on Bartlett St. east of Michigan.

A second Rieth-Riley asphalt crew paved the North Shore and Angela approaches on Michigan St. They then paved surface on the intersection of Main and Marion and the Scottish right drive

Rieth-Riley had a concrete crew that poured the lower apron of the Bartlett roundabout.

Reith Riley had a curb crew that worked on the west side of Main from Jefferson to Colfax.

Reith Riley had a prep crew grading out the 8's in the parking area on Michigan and on Main from LaSalle to Marion. A second crew worked on placing subgrade treatment on Main from bronson to South Street.
  A second Rieth-Riley concrete crew poured cycle track on the north side of Marion between Michigan and Main.

Ziolkowski was on site installing the wall caps on the concrete walls in the center of the Marion roundabout.

Pemberton Davis was working on lighting on Bartlett St. west of the roundabout. The also demolished the old handhole at the northeast corner of the intersection of Main and LaSalle.


Airmarking was on site laying out traffic markings from Marion to Angela on Michigan.

Wisco was on site working on the irrigation at Bartlett. 