Thursday, September 1, 2016

9-1-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Center Aprons and Curb
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Partly Cloudy  PM Partly Cloudy
Hi 73 Lo 58

Rieth-Riley had multiple concrete crews pouring approaches on the east side of Michigan St. between LaSalle and Marion. They also poured the concrete header for the parking stalls on the east side of Michigan.

In the afternoon a Rieth-Riley crew poured the curb at the northwest corner of the intersection of Main and LaSalle.

Rieth-Riley had an asphalt crew that paved the base lift on the east side of Michigan St. from LaSalle to Marion. 

Ziolkowski was on site receiving and beginning to install the planters for the concrete walls in the Marion roundabout.

Pemberton Davis was working on lighting and signage at the Bartlett roundabout. They also had a bor crew trying to get a conduit to the center of the Marion Round About. 

Slussers was on site  prepping for sod on the west side of Michigan north of Bartlett.

Indiana Earth was grading the inside of the Marion roundabout for curb and center aprons. They also worked on grading out behind the sidewalk and curb on Madison and on Main st.

Reith Riley also worked on placing paver mats on Main South of Madison west side and Michigan North of Madison west side.

Wisco was on site with several crews working on Michigan and Marion.