Thursday, September 15, 2016

9-15-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM Sunny  PM Partly Cloudy
Hi 78 Lo 66

Reith Riley had a crew working on pouring concrete at Bronson street to the east of Main. They had a second concrete crew working on pouring side walk and drive way approaches between Colfax and Washington on the west side. A third crew worked on pouring header curb on the west side of Main between Jefferson and Wayne.

Reith Riley had a prep crew working on driveways on the East side of Main Street South of Bronson. A Second prep crew worked on setting Pave Drain on Michigan on the west side between Madison and LaSalle. they also unloaded 2 semi loads of pervious pavers.

Pemberton Davis worked on Detector housings at Bronson and Main, They worked on cutting loops at Navarre and Michigan. They also worked on pushing conduit for lighting at Colfax and Main and Washington and Main area.

Wisco worked on the sprinklers on the North East corner of Michigan and Marion.

Indiana Earth worked on removals on Main street From Colfax to Jefferson on the East side. 

Woodruff worked on setting structures on the south east corner of Main and LaSalle. They then went and adjusted fire hydrants on Main Street at Wayne and in front of the court house. 