Wednesday, September 21, 2016

9-21-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM cloudy PM Mostly Sunny
Hi 84 Lo 62

Reith Riley had a concrete crew work on placing curb on Main Street and Bronson to the east of Main Street. They had a second crew work on pouring bicycle track from Western North to the AT@T building. They then went an poured a drive just North of Wayne on the West side of Main. A third crew poured drive ways and curb between Washington and Colfax on Main. A Fourth crew poured side walk on the east side of Main between LaSalle and Colfax.

Reith Rileys prep crew worked on grading out the paver band from Colfax to LaSalle on the west side of the road. A second crew worked on setting the paver band brick from Madison to Marion on Main Street.

Pemberton Davis is working on the intersection of Colfax and Michigan. They are also working on the Hawk signal at the fire station on Michigan.

Indiana earth is working on removals on the east side of Main St from Washington to Wayne Street. They have a second crew working on rough grading the west side of Main behind the curb from Western to Jefferson.

Wisco is working on the South East quad of Main and Marion. 