9-10-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Cloudy rain PM cloudy rain
Hi 84 Lo 67

Reith Riley had a Asphalt crew pave the approach to the Bartlett Parking Garage Then went home due to the rain.

Reith Riley had a concrete crew pour 150 feet of pavement between Bronson and South Street they went home due to the rain. Reith Riley had a second concrete crew pour the parking stalls in the parking lot of the North East corner of Marion and Michigan. 