Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 74 Lo 56

Reith riley had a concrete crew on Main Street between Bronson and South pouring the mainline pavement. They had a second crew pour the apron on the cul-de-sac to the Bartlett garage theyy then went to main street and poured the alley between Western and Wayne.

Reith Riley had a prep crew working on the drive way approaches along Main Street. on the west side of the road.

Indiana Earth worked on removals on the east side of Main Street between Colfax and Washington.

Pemberton Davis worked on moving the light pole at colfax and Michigan to Indiana and Michigan. They also worked on lighting on Main Street at various locations.

Wisco was on site working on Main between Madison and LaSalle.