Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 82 Lo 58

Reith Riley worked on Pouring concrete on Main Street through the intersection of South Street and to the east on South Street. A Second Concrete crew worked on pouring driveways on the west side of Main Street from Western To Jefferson. A Third concrete crew poured header curb on the west side of Main Street from Jefferson to Washington.

Reith Riley had a prep crew working on drives from Jefferson North to LaSalle. A second prep crew workedon the Pave drain from LaSalle to Marion on Main and Michigan placing chips on the back side.

Indiana earth worked on the removals on the East side of Main from Colfax to Jefferson. 

Pemberton Davis worked on placing conduit in the down town area for street lighting. 

Wisco worked on Main Street from Madison to Marion.