Tuesday, September 27, 2016

9-27-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM Sunny PM Mostly Sunny
Hi 68 Lo 48

Reith Riley Had 3 concrete crews working on the West side of Main Street. at the intersection of Colfax, Jefferson and Washington. Pouring the curbs and ramps. A fourth crew worked on the driveway approach at the ambulance building on Marion.

Reith Riley had a prep crew working on setting tree boxes on the west side of Main. They had a second crew preping for sidewalk on the east side of Main between Jefferson and Washington. They had a third crew placing brick North of LaSalle on the west side of Main.

Woodruff worked on the structures at the intersection of Colfax and Main on the East side.

Pemberton Davis worked at the intersection of South and Main. the light was turned off to allow for the work since it is closed to the east and west.

Indiana earth worked on removals on the Jefferson to the east and west of Main. They worked on Bartlett street and Marion doing miscellaneous work grading. 