Monday, September 26, 2016

9-26-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM cloudy PM Mostly cloudy
Hi 82 Lo 62

Reith Riley worked on pouring sidewalk on the east side of Main Street between Washington and Colfax. They had a second crew work on pouring cycle track on the west side of Main Street between Jefferson and Washington. A third crew worked on pouring cycle track between Washington and Colfax on the west side of Main. A fourth crew poured curb at intersections at various locations between Colfax and Washington curb areas for ramp areas.

Reith Riley had a prep crew working on setting tree grates on the west side of Main Street between Western and Jefferson.

Indiana Earth worked on removals on the east side of Main Street from Wayne to Western and Wayne to Jefferson. A second crew worked on prepping the Ambulance drives on the south side of Marion East of Michigan. A third crew worked on grading out the Bronson to South Street are on Main Street.

C-Tech was on site to set guard rail on the Main Street area between South and Bronson Street. They left after looking at the area and determining that the wrong type of endtreatment was designed for the median area. They will send their recommendations to me and i will forward it on to Structure Point.

Wisco was on site working on the North East and North West quads of Main and Michigan.

Slussers was on site doing the plantings in the Marion round about.

Pemberton Davis worked on the intersections of Main and Wayne and Main and Colfax.

MCI was on site and adjusted hand holes on the west side of various locations.

Woodruff was on site and set structures at the intersection of Main and Colfax. 